Project recovery case study · Portfolio simulation

Recovering an at-risk LMS migration.

A simulated LMS migration reached Week 8 three weeks behind schedule, with testing delayed and the forecast moving beyond the approved budget. I developed a recovery plan that addressed schedule, budget, scope, resource constraints, and the leadership decisions required to protect the core launch date.

RoleProject manager
Project typeLMS migration recovery
Timeline16 weeks · assessed at Week 8
Scope120 courses
Original budget$420,000
DeliverablesControl workbook · Executive brief

01 · Project overview

Diagnose the system, then recover the launch.

Northbridge Technologies was completing a fictional 16-week migration to a new learning management system. By the end of Week 8, content migration, data validation, testing, and launch readiness had fallen behind plan. The forecast had increased from $420,000 to $482,000, and the projected launch had moved from April 26 to May 17.

I approached the scenario as the project manager responsible for diagnosing the delivery problems, evaluating recovery options, resetting the critical path, and presenting leadership with a clear recommendation.

Schedule position3 weeks behindAt the Week 8 assessment
Recommended go-liveApril 26Core launch protected
Recovery EAC$456,0008.6% above baseline
Avoided overrun$26,000Below the no-action forecast

02 · Diagnosis

The delay was interconnected.

The project was not experiencing one isolated problem. Data quality, vendor responsiveness, SME capacity, scope growth, and decision latency were reinforcing one another across the critical path.

01

Data quality

Duplicate learner records and inconsistent transcript fields reduced migration throughput.

02

Vendor defects

Configuration issues remained unresolved beyond the agreed response window, delaying testing.

03

SME capacity

Business experts were balancing project responsibilities with ongoing operational work.

04

Scope growth

Advanced analytics and expanded single sign-on entered the launch scope after planning.

05

Decision delays

Cross-functional questions remained open because ownership and escalation deadlines were unclear.

Week 8 status

Planned progress versus actual progress

Plan to dateActual
Content migration
80%65%
Data validation
75%58%
Administrator UAT
25%0%
Training readiness
20%10%
Launch readiness
15%5%
Working model · Recovery control centerThe dashboard connects schedule, cost, controls, owners, decisions, and readiness in one executive view.

03 · My approach

Focus recovery effort on the critical path.

I evaluated the schedule, cost forecast, scope changes, dependencies, stakeholder responsibilities, and pending leadership decisions. The strategy added capacity only where it relieved the launch path and deferred work that did not protect core learning operations.

01

Reduce launch scope

Move advanced analytics, expanded SSO, and lower-use electives to Phase 2 while preserving compliance reporting and core learning workflows.

02

Add targeted capacity

Use a temporary data migration specialist, parallel UAT groups, and operational backfill where capacity directly relieves the critical path.

03

Tighten delivery controls

Introduce daily data and vendor triage, defect response expectations, objective test exit criteria, and defined severity thresholds.

04

Accelerate decisions

Assign an owner and deadline to each launch, budget, security, and defect decision, then escalate unresolved items through the sponsor.

Executive translation · Recovery strategyThe working diagnosis becomes four actions leaders can evaluate and sponsor.

The recovery plan

Overlap work without removing the controls that protect launch quality.

The revised schedule overlaps selected workstreams while preserving the decisions and quality gates required for launch. Data cleansing, course mapping, configuration remediation, integration testing, and user acceptance testing become the primary critical-path activities.

ScheduleApril 26Core launch restored
Budget$456KRecovery estimate at completion
Avoided overrun$26KBelow no-action forecast
Working model · Recovery scheduleThe schedule makes the revised sequence, dependencies, and critical-path ownership explicit.

04 · Scope and budget

Make the tradeoffs visible.

The recommendation combines targeted investment with deliberate scope reduction. Additional spending is limited to resources that improve the critical path, while noncritical features move to a controlled second phase.

The recovery plan still requires a $36,000 increase over the original budget. The recommendation makes that tradeoff visible rather than presenting the recovered schedule as cost neutral.

Recommended recovery decisions and modeled impacts
DecisionCost impactSchedule impactPurpose
Data specialist+$15,0005 days recoveredIncrease data cleansing throughput
Parallel UAT groups+$6,0007 days recoveredTest workstreams concurrently
Move analytics to Phase 2-$22,00010 days recoveredRemove noncritical launch scope
Three-year transcript window-$8,0004 days recoveredReduce initial migration volume

Schedule impacts overlap; recovered days are not additive.

Working model · Budget recovery forecastThe forecast reconciles baseline, actuals, commitments, recovery costs, and remaining contingency.
Executive translation · Budget and scope tradeoffsThe detailed forecast is distilled into the decision leaders need to make.

05 · Leadership governance

Recovery depends on decision speed.

I created a decision log that assigns ownership and due dates to final go-live authorization, residual defect acceptance, Phase 2 funding, and other decisions affecting launch readiness.

Daily

Delivery triage

Vendor defects and data quality.

Twice weekly

Steering decisions

Open decisions and operational readiness.

Weekly

Executive outlook

Forecast, risks, and launch readiness.

Escalation threshold

Act before recovery erodes

Escalate if the forecast exceeds $456,000, the launch date slips, a critical security defect remains open, or a readiness measure misses target.

Executive translation · Final recommendationThe launch remains achievable if leadership holds the reduced scope, maintains targeted capacity, and closes go-live decisions by April 23.

06 · Project artifacts

Analysis for the team. Clarity for leadership.

The workbook proves the analysis and control logic. The executive brief shows how I translated that working model into a concise recommendation for leadership.

Executive recovery brief

Eight-slide leadership presentation

Summarizes the project baseline, root causes, recovery strategy, revised critical path, budget tradeoffs, and decisions required before launch.

Recovery control workbook

Editable project control system

Contains the executive dashboard, recovery schedule, budget forecast, change log, decision log, stakeholder plan, and project assumptions.

Skills demonstrated

  • Project recovery planning
  • Critical-path analysis
  • Schedule management
  • Budget forecasting
  • Scope control
  • Change management
  • Risk and dependency management
  • Executive communication
  • Decision governance
  • Stakeholder planning
  • LMS implementation
  • Learning operations
Evidence standard

This is a portfolio simulation. Dates, organization details, project data, and modeled recovery outcomes are fictional and are presented to demonstrate project management judgment, analysis, controls, and executive communication.